Compare Building Permit Fees by Jurisdiction (2026)

Side-by-side comparisons using actual fee formulas from official .gov fee schedules. The same project can cost significantly more in one county than the next.

About These Comparisons
  • Each comparison uses only data verified against official .gov fee schedule documents - no estimated or inferred values.
  • Comparisons are added as jurisdiction pages go live. Currently live: Fairfax, Loudoun, Chesterfield, Henrico Counties and Richmond City, VA.
  • Use the fee calculator for a quick Fairfax estimate or go to the jurisdiction page for the full formula breakdown.
  • Always verify fees directly with your local building department before budgeting or filing.
Live Comparisons

Virginia Jurisdiction Comparisons

Side-by-side comparisons using verified fee data from official fee schedules.

Virginia Live
Fairfax County vs Loudoun County
Head-to-head permit fee comparison
$15,000 deck - which costs more?
Virginia Live
Chesterfield County vs Henrico County
Flat fee vs value-based formula
Crossover at ~$63,000 - both verified
Virginia Live
Fairfax County vs Chesterfield County
Percentage formula vs flat fees
$688.50 vs $166.28 - Chesterfield always cheaper
Hampton Roads Live
Norfolk City vs Virginia Beach City
Flat fees and area tiers vs sq-ft and value formulas
Norfolk wins alterations and pools, VB wins decks - both verified
Virginia Live
Fairfax County vs Richmond City
3% of cost + plan review vs $63 base + per-$1,000 increment
$1,377 vs $237.62 ($30k alteration) - Richmond cheaper across the board
Virginia Live
Richmond City vs Virginia Beach City
Value-only formula vs sq-ft hybrid (decks, additions, new build)
Crossover at ~$100k value - VB wins anything priced by sq ft
Virginia Live
Henrico County vs Richmond City
$100 base + $6/$1k over $5k (capped at $680) vs $63 + $6.07/$1k over $2k (no cap)
$163.20 vs $144.75 ($15k deck) - Richmond cheaper under ~$103k; Henrico wins above the cap
DC + Virginia Live
Washington DC vs Fairfax County
DC tier formula + 10% Enhanced + Green Building Fee vs Fairfax 3% + 50% plan review + 2% levy
$735.90 vs $1,377 ($30k alteration) - DC saves $641; Fairfax wins per-sq-ft new SFD
DMV vs Richmond MSA Live
Fairfax County vs Henrico County
Fairfax 3% + 50% plan review vs Henrico $100 + $6/$1k over $5k (capped at $680)
$1,377 vs $255 ($30k alteration) - Henrico dramatically cheaper for nearly all residential work
Capital pair Live
Washington DC vs Richmond City
DC tier formula + 10% Enhanced + Green Building Fee vs Richmond $63 + $6.07/$1k over $2k
$735.90 vs $237.62 ($30k alteration) - Richmond cheaper for alterations; DC wins on new SFD
Hampton Roads vs DMV Live
Norfolk City vs Fairfax County
Norfolk flat $100 alteration vs Fairfax 3% of cost + 50% plan review
$152 vs $1,377 ($30k alteration) - Norfolk dramatically cheaper for most work
Virginia In Progress
Fairfax vs Prince William County
Awaiting Prince William fee verification
Page launching soon
Virginia In Progress
Fairfax vs Arlington County
Awaiting Arlington fee verification
Page launching soon

Comparisons are added as jurisdiction fee data is verified. Each comparison requires confirmed source data from both jurisdictions before publishing.

Virginia Permit Fee Quick Reference

Live data for Fairfax, Loudoun, Chesterfield, Henrico Counties and Richmond City, VA. Additional jurisdictions will be added as fee data is verified.

Jurisdiction Base Fee Method Plan Review State Levy $15K Deck (All-In) Status
Fairfax County 3% of cost · min $72 50% of permit fee 2% (USBC) $688.50 Verified
Loudoun County $395 flat (≤1,000 sq ft) · 1% (larger) Bundled in flat fee 2% (USBC) ~$402.90 (est.) Estimated
Chesterfield County Flat fee by project type ($114 deck · $399 addition) Bundled (not listed separately) 2% (USBC) $166.28 Verified
Henrico County $100 + $6/$1,000 over $5,000 · max $680 Not listed separately 2% (USBC) $163.20 Verified
Richmond City $63 + $6.07/$1,000 over $2,000 · no cap Not listed separately 2% (USBC) $144.75 Verified
Prince William County Verification in progress TBD 2% (USBC) TBD In Progress
Arlington County Verification in progress TBD 2% (USBC) TBD In Progress
City of Alexandria Verification in progress TBD 2% (USBC) TBD In Progress

All Virginia jurisdictions collect the 2% USBC state levy (Code of VA §36-139). The base fee method and plan review rate are set independently by each jurisdiction. TBD values will be filled as official fee schedules are verified.

Always verify current permit fees directly with your local building department before budgeting or filing. Fee schedules change annually. Contact your county or city building department for current rates.
Disclaimer: All fee information on PermitPrice is for informational purposes only and is not an official permit quotation. Actual fees are determined by the applicable building department at the time of application. Verify all fees directly with the relevant building department before filing.

Written by: Munib Ur Rehman

Data verified against official fee schedule documents.