Virginia Building Permit Fees (2026)

Actual fee formulas from official Virginia jurisdiction fee schedules. Each county and city sets its own rates - all include Virginia's mandatory 2% USBC state levy.

State
Virginia (VA)
Fee Structure
Locality-set + state levy
State Levy (All Jurisdictions)
2% USBC levy (Code of VA §36-139)
Plan Review
Jurisdiction-specific (typically 50%)
Jurisdictions Covered
1 live · more in progress
Verified By
Munib Ur Rehman · April 2026
Key Takeaways
  • Virginia has no single statewide building permit fee. Each county and independent city sets its own fee schedule.
  • All Virginia jurisdictions must collect a 2% USBC state levy on every building permit (Code of VA §36-139).
  • Plan review fees are separate from the building permit fee - Fairfax County charges 50% of the permit fee for plan review.
  • Trade permits (electrical, plumbing, HVAC) are issued separately with their own fee tiers in every Virginia jurisdiction.
  • Fee schedules change each fiscal year. Verify with your local building department before budgeting or filing.

How Virginia Building Permit Fees Work

Every Virginia building permit invoice has the same three-layer structure, regardless of jurisdiction. The rates differ by locality - the layers do not.

Fee Layer Who Sets It Fairfax County Example Authority
Building Permit Fee Local jurisdiction (county or city) max(cost × 3%, $72 min) Local fee schedule
Plan Review Fee Local jurisdiction Permit fee × 50% Local fee schedule
Virginia USBC State Levy State-mandated · collected locally (Permit + Plan Review) × 2% Code of VA §36-139

The 2% USBC levy is the one constant across all 95 Virginia counties and 38 independent cities. It is collected by the local building department and remitted to the Virginia Department of Housing and Community Development to fund code training and enforcement programs.

Virginia Permit Fees: What Most Homeowners Miss

Real-World Example: Why the All-In Number Matters

$15,000 residential deck project · Fairfax County, VA · Fee schedule: Appendix Q FY2025 (effective July 1, 2024)

Building Permit Fee (max(3% × $15,000, $72)) $450.00
Plan Review Fee ($450 × 50%) $225.00
Virginia USBC State Levy ($675 × 2%) $13.50
Total Building Permit Fees $688.50

Generic guides typically quote $300-$500 for this project. The $688.50 all-in figure comes directly from Fairfax County's Appendix Q fee schedule, verified March 15, 2026.

When Virginia Permit Fee Estimates Break Down

  • Using Fairfax rates for other counties: Each county adopts its own fee ordinance. Prince William County and Arlington County have different base rates, minimums, and plan review percentages. Never apply Fairfax formulas to other jurisdictions.
  • Omitting trade permits: Electrical, plumbing, and HVAC permits are always separate in Virginia. A deck with electrical lighting requires a separate electrical trade permit at an additional cost not covered here.
  • Annual rate changes: Most Virginia jurisdictions update fee schedules on July 1 with the new fiscal year budget. Fees from a prior year may be materially different from current rates.
  • Independent cities vs. counties: Virginia's 38 independent cities (Alexandria, Arlington is a county, not a city) are legally separate from surrounding counties and often have different fee schedules.
  • Project scope changes: If construction value increases after a permit is issued, most Virginia jurisdictions require a permit amendment and may charge additional fees on the difference.

Frequently Asked Questions

No. Virginia does not have a uniform statewide building permit fee. Each of Virginia's 95 counties and 38 independent cities adopts its own fee schedule by ordinance. The only fee that is the same statewide is the 2% USBC state levy, which is collected by each jurisdiction and remitted to the Virginia Department of Housing and Community Development under Code of Virginia §36-139.
The Virginia Uniform Statewide Building Code (USBC) levy is a 2% surcharge on the combined building permit fee and plan review fee. It applies to every building permit in Virginia. The local building department collects it and remits it to the state. The levy funds the Virginia Building Code Academy and state code enforcement training programs. On a Fairfax County $15,000 deck with a $450 permit fee and $225 plan review, the levy is ($450 + $225) × 2% = $13.50.
The cost depends on your specific jurisdiction. In Fairfax County, a $15,000 deck building permit costs $688.50 all-in (permit + plan review + state levy). Other Virginia counties have different base rates and plan review percentages. Use the fee calculator or find your jurisdiction's page on PermitPrice for the actual formula that applies to your project.
Plan review requirements vary by jurisdiction and project type. In Fairfax County, plan review is mandatory for all residential building permits and costs 50% of the base permit fee. Other Virginia jurisdictions may have different thresholds - some exempt small-value projects below a certain dollar amount from plan review. Check your specific jurisdiction's fee schedule or building department website for the applicable rule.
Yes. In Virginia, electrical, plumbing, and HVAC (mechanical) work each require a separate trade permit. Building permit fees do not include trade permit fees. In Fairfax County, an electrical trade permit for a new 200-amp service runs $341-$633 depending on amperage. These fees are in addition to the building permit, plan review, and state levy. Always budget for trade permits when planning a renovation project.
The most reliable source is your county or city building department's website. Look for a "fee schedule," "building permit fees," or "fee ordinance" document - usually a PDF updated annually. Virginia jurisdictions are required to publish adopted fee schedules. If you cannot find the schedule, call your local Land Development Services or building inspections office directly. PermitPrice publishes verified fee formulas for jurisdictions we have researched, with direct links to the source documents.

Sources

Official .gov Sources · Verified April 2026
Next Step

Know your jurisdiction? Go directly to the fee formula page.

Permit Fees Are One Part of Your Project Budget

Once you know your permit cost, two related numbers round out your total budget picture:

Property tax impact after your project closes

A finished deck or addition increases your assessed value in Virginia. See how each jurisdiction calculates ongoing property taxes at CountyTaxTools.com.

Planning new construction or a large addition?

Development impact fees and zoning costs in Virginia can exceed the building permit fee significantly. Research them at ZoneFee.com.

Always verify current fees directly with your local Virginia building department before budgeting or filing. Fee schedules are adopted annually and change on July 1 of each fiscal year. Contact your county or city Land Development Services or Building Inspections office for current rates.
Disclaimer: All fee information on PermitPrice is for informational purposes only and is not an official permit quotation. Actual permit fees are determined by the local building department at the time of application. Fee schedules, surcharge rates, and permit requirements can change without notice. Verify all fees directly with the applicable building department before filing.

Written by: Munib Ur Rehman

Data verified against official fee schedule documents.