Frisco, TX Building Permit Fees (2026)

Actual residential building permit fees for the City of Frisco (Collin and Denton Counties, DFW Metroplex), read from the Permit, Inspection and Miscellaneous Consolidated Fee Schedule, updated October 7, 2025. Frisco prices new construction on a tiered per-square-foot table and gives most other residential projects - decks, fences, pools, solar, re-roofs - explicit flat fees. Every figure below is read directly from the current fee schedule.

Jurisdiction
Frisco, TX (Collin & Denton Counties)
Permit Type Covered
Building permit (residential)
Coverage Scope
Tiered per-SF new construction + flat project fees
Fee Schedule Effective
Updated October 7, 2025
Last Verified
August 29, 2026 (live PDF)
Fee Status
Official schedule - figures exact
What This Page Covers - and What It Does Not

This page covers: The residential building permit fees in Frisco's Consolidated Fee Schedule - the tiered per-square-foot table for new single-family construction and additions (a 2,500 sq ft home is $1,185), plus the flat fees for decks, patio covers, sheds, fences, solar, retaining walls, demolition, re-roofs, general alterations, window and door replacement, foundation repair, and swimming pools.

The application fee is part of the permit fee, not an add-on: Frisco collects a non-refundable application fee of $300 for residential new construction/additions and $50 for alterations. The schedule states verbatim that this "is not an additional permit fee but is a non-refundable portion of the same building permit fee" - it is paid up front and credited toward the permit fee rather than stacked on top.

Trades can be separate: standalone electrical and mechanical permits carry a $50 issuance fee plus per-square-foot and per-appliance components. Plumbing trade fees are on schedule pages that were not fully captured and are not published here - confirm them with Building Inspections rather than assuming.

Texas has no statewide levy: Texas adds no state-level building permit surcharge, and Frisco lists no separate technology or percentage surcharge line. Any online-payment convenience fee is outside this schedule.

This page does NOT cover: Impact and development fees, zoning and planning application fees, water and sewer tap fees, platting fees, and Collin/Denton County, MUD, PID, or HOA costs. These are separate and are not included in any figure here.

Key Takeaways
  • New single-family construction and additions are priced per gross square foot on a tiered table: $150 for the first 300 sq ft plus $0.50 per additional sq ft up to 1,999 sq ft, then fixed base-plus-increment tiers from 2,000 sq ft up. A 2,500 sq ft home is $1,185 - the schedule's own worked figure.
  • Frisco's $300 residential application fee (and $50 for alterations) is a non-refundable portion of the building permit fee, not an extra charge on top. You pay it at submittal and it is credited toward the permit fee.
  • Most residential projects are flat lines: below-ground pool $200 (with spa $275, above-ground $100), fence $75, solar $75, modular shed $50, re-roof $150, demolition $50, foundation repair $75, and windows/doors $75 plus $25 each additional element up to a $150 cap.
  • Decks, patio covers, arbors, and conventionally framed sheds are $75 plus $0.59 per gross square foot, capped at $550. General alterations are $75 plus $0.45 per gross square foot, also capped at $550.
  • Texas has no statewide percentage permit levy - unlike Virginia's 2% USBC add-on - and Frisco prints no separate surcharge line. Standalone electrical and mechanical permits carry a $50 issuance fee plus per-square-foot and per-appliance components; plumbing trade fees are not published here and should be confirmed with Building Inspections.
  • The schedule is current. The Consolidated Fee Schedule footer reads "Updated 10-7-2025," and the figures on this page were confirmed against the live PDF on August 29, 2026. Confirm current amounts with the Building Inspections Division before budgeting.

Frisco Building Permit Fee Structure

Frisco runs two systems side by side. New single-family construction and additions are priced per gross square foot on a tiered table. Everything else - decks, fences, pools, solar, re-roofs, and other common projects - has an explicit flat or flat-plus-per-square-foot fee. The tables below reproduce the figures exactly as printed in the Consolidated Fee Schedule (updated October 7, 2025).

New construction and additions - tiered per gross square foot

Gross square footage Building permit fee
1 to 1,999$150 for first 300 SF + $0.50 each additional SF
2,000 to 2,499$1,000 for first 2,000 SF + $0.37 each additional SF
2,500 to 2,999$1,185 for first 2,500 SF + $0.35 each additional SF
3,000 to 3,499$1,360 for first 3,000 SF + $0.34 each additional SF
3,500 to 3,999$1,530 for first 3,500 SF + $0.33 each additional SF
4,000 to 4,499$1,695 for first 4,000 SF + $0.32 each additional SF
4,500 to 4,999$1,855 for first 4,500 SF + $0.31 each additional SF
5,000 to 5,499$2,010 for first 5,000 SF + $0.30 each additional SF
5,500 to 5,999$2,160 for first 5,500 SF + $0.29 each additional SF
6,000 to 6,499$2,305 for first 6,000 SF + $0.29 each additional SF
6,500 to 6,999$2,450 for first 6,500 SF + $0.28 each additional SF
7,000 and up$2,590 for first 7,000 SF + $0.26 each additional SF

Square footage is measured as gross area. The $300 residential application fee (or $50 for alterations) is a non-refundable portion of the building permit fee, paid at submittal - not an amount added on top of the tier figure.

Flat fees for common residential projects

Project Fee
Swimming pool, below ground$200.00
Swimming pool, below ground, with spa$275.00
Swimming pool, above ground$100.00
Swimming pool / spa permit (base)$75.00
Splash pad$100.00
Pool demolition$50.00
Fence$75.00
Solar installations$75.00
Deck / patio cover / arbor / framed shed$75 + $0.59 per gross SF (max $550)
Modular shed$50.00
Re-roof permit$150.00
General alterations$75 + $0.45 per gross SF (max $550)
Windows / doors replacement$75 + $25 each additional element (max $150)
Foundation repair$75.00
Retaining walls / screening walls$150 per wall ($300 per subdivision)
Demolition permit$50.00
Certificate of Occupancy change$100.00

Application, plan review, and trade permits

Item Fee Notes
Residential new application fee$300.00Non-refundable portion of the building permit fee, not an add-on
Alterations application fee$50.00Non-refundable portion of the permit fee
Residential building plan reviewBundledNo standalone percentage-based residential plan review; built into the permit fee
Plan revision review$50.00 per hourCharged on revisions
Electrical permit (standalone)$50 issuance + $0.03/gsfPlus $4.75 per residential appliance; meter release $45
Mechanical permit (standalone)$50 issuance + $0.05/gsfPlus per-appliance furnace/boiler/air-handler fees
Plumbing permit (standalone)Not published hereOn schedule pages not fully captured - confirm with Building Inspections

Frisco lists no separate statewide or percentage technology surcharge. The plumbing trade permit fees were on schedule pages not fully captured during extraction and are deliberately left unpublished rather than guessed - confirm them directly with the Building Inspections Division.

Frisco Permit Fee Components and Surcharges

A Frisco residential total is unusually simple to read: for a flat-fee project it is a single line, and for new construction it is the tier figure with the $300 application portion already inside it. There is no statewide levy and no percentage technology surcharge.

Component Amount Status
New construction building permit Tiered per gross SF Exact from the fee schedule
Residential application fee $300 ($50 alterations) Non-refundable portion of the permit fee, not an add-on
Flat project fees $50 to $275 depending on project Pool, fence, solar, shed, re-roof, etc.
Residential plan review Bundled into permit fee No standalone percentage line
Standalone electrical / mechanical permits $50 issuance + per-gsf/appliance Separate when pulled on their own
Plan revision review $50.00 per hour Charged on revisions
Texas statewide levy $0.00 Texas imposes none
Impact, tap, platting fees Separate schedules Excluded from every figure here

No technology, automation, or credit-card surcharge appears on the residential lines of the Consolidated Fee Schedule, and Texas imposes no state-level permit levy. Any convenience fee charged by Frisco's online permit portal is a payment-processing charge outside this schedule.

Worked Examples

Every figure below is direct from the Consolidated Fee Schedule (updated October 7, 2025). New-construction lines follow the tiered table; project lines are flat or flat-plus-per-square-foot as printed.

Example 1: New 2,500 SF Single-Family Home

Fee Calculation - New 2,500 SF Home in Frisco, TX
Fee Component Rule Applied Amount
Building permit fee 2,500 SF tier: $1,185 for first 2,500 SF $1,185.00
of which application fee (non-refundable portion) paid at submittal, credited to permit fee $300.00
Standalone electrical permit (if pulled) $50 issuance + $0.03/gsf $125.00

Assumptions: A 2,500 sq ft home is the first value in the 2,500-2,999 tier, so the building permit fee is $1,185.00 - the schedule's own worked figure and exact. The $300 residential application fee is a non-refundable portion of that $1,185, paid at submittal, not an amount added on top (the schedule states it "is not an additional permit fee"). The electrical line is illustrative: $50 issuance plus $0.03 per gross sq ft on 2,500 sq ft is $75, for $125 if the electrical is pulled as its own permit. Source: Frisco Consolidated Fee Schedule (updated 10-7-2025).

Example 2: Below-Ground Pool, Deck, and Flat Projects

Fee Calculation - Flat Residential Projects in Frisco, TX
Project Rule Applied Amount
Below-ground swimming pool flat line $200.00
200 SF deck $75 + 200 × $0.59 $193.00
Fence flat line $75.00
Solar installation flat line $75.00
Re-roof flat line $150.00

Assumptions: The pool, fence, solar, and re-roof lines are flat and exact from the schedule. The deck is $75 plus $0.59 per gross square foot: on 200 sq ft that is $75 + $118 = $193, under the $550 cap. A standalone electrical permit for the pool ($50 issuance + components) or a spa upgrade ($275 below-ground-with-spa line) would change the pool total. Source: Frisco Consolidated Fee Schedule (updated 10-7-2025).

Example 3: Windows, Doors, and a Modular Shed

Fee Calculation - Replacement and Accessory Projects in Frisco, TX
Project Rule Applied Total
Replace 4 windows $75 + 3 × $25 (first element included) $150.00
Modular shed flat line $50.00
Foundation repair flat line $75.00
Demolition permit flat line $50.00

Assumptions: Windows/doors are $75 plus $25 each additional element, capped at $150 - four windows reach the $150 cap. The modular shed, foundation repair, and demolition lines are flat and exact. A conventionally framed shed would instead price at $75 + $0.59 per gross sq ft (max $550). Source: Frisco Consolidated Fee Schedule (updated 10-7-2025).

Read before you budget from these examples

  • The $300 application fee is inside the permit fee. For a new home it is a non-refundable portion of the tier figure, not a separate charge added to it. The schedule states this verbatim; still, confirm the collection mechanics with Building Inspections before budgeting cash flow.
  • Flat lines are exact. Pool $200, fence $75, solar $75, re-roof $150, modular shed $50, demolition $50 - each is a single printed line.
  • Trades can be separate. A standalone electrical or mechanical permit adds a $50 issuance fee plus per-square-foot and per-appliance components. Plumbing trade fees are not published here.
  • Excluded fees are large. Impact and development fees, water and sewer tap fees, and platting fees sit on separate schedules and are not in any figure above.

Practitioner Insight

Frisco has one of the friendliest fee schedules to read in the DFW Metroplex because it does two things most cities do not: it prints an explicit flat fee for nearly every common residential project, and it folds plan review into the permit fee instead of stacking a separate percentage. For a homeowner adding a pool, a deck, or solar, the number on this page is the number - $200, a deck at $75 + $0.59/sq ft, or $75 for solar - with no plan-review multiplier to chase.

The one line that trips people up is the $300 residential application fee. It reads like an add-on, but the schedule is explicit that it "is not an additional permit fee" - it is a non-refundable portion of the same building permit fee, collected at submittal. So a 2,500 sq ft new home is $1,185 total, not $1,485. Where Frisco can still surprise you is on the site side: impact and development fees, water and sewer tap fees, and platting are all separate and, on a new home in a growing suburb, can dwarf the permit itself. Compare Frisco's flat-fee approach to nearby DFW cities like Carrollton, Plano, and McKinney.

Permit Requirements - Common Residential Projects in Frisco

Project Type Permit Required? Fee Category Notes
New single-family home Yes Tiered per gross SF 2,500 SF = $1,185 (application fee included)
Room addition Yes Tiered per gross SF Same tiered table as new construction
Swimming pool (below ground) Yes $200.00 flat With spa $275; above ground $100
Deck / patio cover Yes $75 + $0.59/gsf (max $550) Same rate for arbors and framed sheds
Fence Yes $75.00 flat Any length/height/material
Rooftop solar Yes $75.00 flat A separate electrical permit may apply for interconnection
Re-roof Yes $150.00 flat Any roof size
Windows / doors replacement Yes $75 + $25 each additional (max $150) Four elements reach the $150 cap
Foundation repair Yes $75.00 flat Standalone line
Demolition Yes $50.00 flat Pool demolition also $50
Modular shed Yes $50.00 flat Framed shed uses the deck rate instead

Permit trigger thresholds and whether a project needs a separate trade permit are set by the City of Frisco Building Inspections Division. Where a project is not listed, confirm the applicable line before filing rather than assuming a flat fee.

City of Frisco Building Inspections Division

Department

Development Services - Building Inspections Division

George A. Purefoy Municipal Center, 6101 Frisco Square Blvd, 3rd Floor, Frisco, TX 75034

Contact

972-292-5301

Building Inspections Division - call to confirm the current fee and whether a separate trade permit is required.

Fee Schedule

Consolidated Fee Schedule

Permit, Inspection and Miscellaneous Consolidated Fee Schedule · updated October 7, 2025

Verify with your local building department before budgeting or filing. The fees on this page come from the City of Frisco Permit, Inspection and Miscellaneous Consolidated Fee Schedule, updated October 7, 2025 and confirmed against the live PDF on August 29, 2026. Confirm the current amount, whether a separate trade permit is required for your project, and the plumbing trade fees (not published here) with the Building Inspections Division at 972-292-5301 before treating any total on this page as final.

When This Estimate May Not Apply

Your project needs a separate trade permit

A flat project fee covers the building permit for that project, but standalone electrical and mechanical work adds a $50 issuance fee plus per-square-foot and per-appliance components. Plumbing trade fees are not published on this page - confirm them with Building Inspections.

You read the $300 application fee as an add-on

The schedule states the residential application fee "is not an additional permit fee but is a non-refundable portion of the same building permit fee." Treat a 2,500 sq ft home as $1,185 total, with $300 of that paid up front - not $1,485. Confirm the collection mechanics with the department.

Your deck or alteration exceeds the cap

A deck, patio cover, arbor, or framed shed is $75 + $0.59 per gross sq ft but capped at $550, and general alterations are $75 + $0.45 per gross sq ft capped at $550. Very large projects hit the cap; smaller ones pay the per-square-foot amount.

You are budgeting site and utility costs

Impact and development fees, water and sewer tap fees, and platting fees are set on separate schedules and are not in any figure on this page. On a new home in Frisco these can exceed the building permit itself.

The city adopts a new fee schedule

These figures are from the Consolidated Fee Schedule updated October 7, 2025 and confirmed live on August 29, 2026. Frisco references a broader citywide fee schedule that can be updated; confirm the current building-permit amount before filing.

Source note: Figures were extracted with pdfplumber from the City of Frisco Permit, Inspection and Miscellaneous Consolidated Fee Schedule (footer "Updated 10-7-2025") and re-confirmed on August 29, 2026 by re-downloading the live PDF from friscotexas.gov and re-reading the fence ($75), solar ($75), below-ground pool ($200), deck ($75 + $0.59/sq ft), re-roof ($150), demolition ($50), and modular shed ($50) lines - all matched. The residential building plan review is bundled into the permit fee; the plumbing trade permit fees were on schedule pages not fully captured and are deliberately left unpublished rather than guessed.

Frequently Asked Questions

For new construction, Frisco uses a tiered per-gross-square-foot table: a 2,500 sq ft home is $1,185 (which already includes the $300 non-refundable residential application portion). Most other residential projects are flat: a below-ground pool is $200, a deck is $75 + $0.59/sq ft, and fence, solar, or modular-shed permits start at $75. Texas has no statewide levy.
No. The Consolidated Fee Schedule states the residential application fee "is not an additional permit fee but is a non-refundable portion of the same building permit fee." So a 2,500 sq ft home is $1,185 total, with $300 paid up front at submittal and credited toward the permit fee - not $1,485. Alterations carry a $50 application portion.
A below-ground swimming pool is a flat $200, a below-ground pool with a spa is $275, and an above-ground pool is $100. A separate electrical permit may apply for pool equipment. Our Frisco pool permit cost guide works through the pool lines in detail.
A fence is a flat $75, a re-roof is a flat $150, and a deck is $75 plus $0.59 per gross square foot, capped at $550 - so a 200 sq ft deck is $193. Patio covers, arbors, and conventionally framed sheds use the same deck rate; a modular shed is a flat $50.
A solar installation permit is a flat $75. A separate electrical permit ($50 issuance plus components) may apply for the interconnection, which this page does not fold into the $75. Our Frisco solar permit cost guide covers that in detail.
There is no standalone percentage-based residential plan review fee - it is bundled into the building permit fee - and Texas imposes no statewide levy. A plan revision review is $50 per hour if you resubmit. Any online-portal convenience fee is a payment-processing charge outside the schedule.
For new construction the trades are part of the project, but standalone electrical and mechanical permits carry a $50 issuance fee plus per-square-foot ($0.03/gsf electrical, $0.05/gsf mechanical) and per-appliance components. Plumbing trade fees were on schedule pages not fully captured and are not published here - confirm them with Building Inspections.
Current. The Consolidated Fee Schedule footer reads "Updated 10-7-2025," and the figures on this page were re-confirmed against the live PDF on August 29, 2026. Frisco references a broader citywide fee schedule that can be updated, so confirm the current building-permit amount before filing. Compare with other Texas cities on the Texas permit fees hub.

Sources

Official .gov Sources ยท Verified August 2026
Next Step

Read a Frisco project guide, or compare another verified DFW city.

Texas Permit Fees Hub → Frisco Pool Permit Guide → Frisco Solar Permit Guide → Carrollton Permit Fees → Plano Permit Fees → McKinney Permit Fees → Permit Fee Calculator →

Permit Fees Are One Part of Your Project Budget

Once you know your Frisco permit cost, two related numbers round out your total budget picture:

Property tax impact after your project closes

A permitted addition, pool, or new home can change the property's taxable value in Collin or Denton County. The county appraisal district determines that value and local taxing units adopt the rates, both separately from this permit fee.

Impact, tap, and platting fees for larger projects

Frisco's impact and development fees, water and sewer tap fees, and platting fees sit on schedules separate from the building permit. These items are governed separately and are not included in the figures above.

These charges are administered separately from the building permit fee, though the responsible office and billing process vary by jurisdiction. See which tool covers each charge →

Always verify current fees directly with the City of Frisco Building Inspections Division before budgeting or filing. The fees on this page are from the Permit, Inspection and Miscellaneous Consolidated Fee Schedule, updated October 7, 2025 and confirmed live on August 29, 2026. Frisco references a broader citywide fee schedule that can be amended - confirm the current amount, whether a separate trade permit is required, and the plumbing trade fees with the Building Inspections Division at 972-292-5301 before you file.
Disclaimer: All fee information on PermitPrice is for informational purposes only and is an estimate, not an official permit quotation. Actual permit fees are determined by the City of Frisco Building Inspections Division at the time of application. The tiered new-construction figures, the $300/$50 application fee, and the flat pool, fence, solar, deck, re-roof, shed, demolition, windows/doors, and foundation-repair lines shown are exact from the Consolidated Fee Schedule, updated October 7, 2025. The $300 residential application fee is a non-refundable portion of the building permit fee, not an add-on. Plumbing trade permit fees are not published on this page because they were on schedule pages not fully captured. Impact and development fees, water and sewer tap fees, platting fees, and Collin/Denton County, MUD, PID, and HOA costs are set on separate schedules and are not included in any figure here. Verify all fees directly with the department before filing.

Written by: Munib Ur Rehman

Data verified against official fee schedule documents.