Residential swimming pool permit fees for the City of Laredo, Texas, pulled directly from the Code of Ordinances, Chapter 7, Section 109.2 Schedule of Permit Fees. Laredo prices a swimming pool as a flat $64.00 building permit - the same at any pool size or value, because it is a flat line, not a valuation-based fee. City Ordinance No. 2024-O-247 adds a flat $20.00 technology fee to every residential permit, so the pool permit comes to $84.00. That still makes Laredo one of the least expensive verified Texas cities for a pool building permit. One caution: the schedule's residential plan-checking fee for a pool was not captured, so this guide reports the $64 building permit plus the $20 technology fee and does not add an unconfirmed plan-check line. Texas has no statewide permit levy, and Laredo adds no percentage surcharge.

Swimming Pool Permit
$64.00 flat (building permit)
Technology Fee
$20.00 ($84.00 with permit)
Fee Basis
Flat - not valuation-based
Pool Plan-Check Fee
Not printed - confirm with department
Pool Electrical / Barrier
Separate - not in the $84
State / City Percentage Levy
None (Texas has no state levy)
Fee Status
Codified schedule - no printed effective date, verify current
What This Guide Covers - and What It Does Not

This guide covers: The City of Laredo (Webb County) swimming pool building permit fee as printed in Section 109.2 of the Code of Ordinances - a flat $64.00 - plus the $20.00 residential technology fee from Ordinance No. 2024-O-247, for $84.00. The permit and technology-fee figures are both printed in the codified schedule or the ordinance, so the $84 is exact (before any plan-check fee) and is the same whether the pool is a small plunge pool or a large in-ground pool.

The pool plan-check fee is not confirmed: Section 109.2 charges a residential plan-checking fee for some project types, but the captured schedule only reproduced the block-fence ($30) and re-roof ($34) plan-check rows. A pool plan-check fee is not printed here and is not estimated - if one applies, it would be added on top of the $84. Confirm with Building Development Services before budgeting.

The technology fee applies per permit: Ordinance No. 2024-O-247 (effective about December 27, 2024, sixty days after the October 28, 2024 public hearing) assesses the $20.00 technology fee to "every residential permit." If your project needs more than one permit (for example a separate electrical permit or a separate barrier permit), each permit may carry its own $20. PermitPrice adds it once, for the single pool permit shown.

Pool electrical and the safety barrier are separate: the $84 covers the pool building permit and its technology fee. Pool pump and equipment wiring may draw a separate electrical permit, and a code-required safety barrier is handled on its own (a block-fence barrier is $46 + $30 plan check + $20 technology fee = $96 - see the Laredo fence permit guide). Whether the barrier needs a separate permit is a department determination.

This guide does NOT cover: pool construction cost, impact or utility tap fees, gas-line permitting for a pool heater, HOA approvals, or zoning setback questions. Zoning, platting, impact, and utility fees are separate schedules and are not included.

Key Takeaways
  • Laredo charges a flat $64.00 for a swimming pool building permit - the same fee regardless of pool size or construction value, because it is a flat line, not a valuation-based schedule. Ordinance No. 2024-O-247 adds a flat $20.00 technology fee to every residential permit, so the pool permit is $84.00.
  • A residential plan-checking fee for a pool was not captured from the codified schedule, so this guide reports the $64 building permit plus the $20 technology fee ($84) and does not add an unconfirmed plan-check line. If one applies, it is on top of the $84 - confirm with the department.
  • Pool pump and equipment wiring may draw a separate electrical permit, and a code-required safety barrier is handled separately (a block-fence barrier is $96 all-in). Neither is included in the $84.
  • Texas has no statewide percentage permit levy - unlike Virginia's 2% USBC add-on - and Laredo adds no city percentage surcharge on the pool permit. The only add-on is the flat $20.00 residential technology fee.
  • For context among verified Texas cities: Laredo's $84 pool permit ($64 flat building permit + $20 technology fee) is still one of the lowest, above McAllen's $55.86 and well below Brownsville's $200, San Marcos's $286, and College Station's ~$301 valuation-based pool fee - though those cities' figures include or exclude trades differently.
  • The figures come from the current codified Laredo Code of Ordinances (Chapter 7, Section 109.2), captured June 13, 2026. The fee table carries no single printed effective date; Chapter 7 was last amended in 2024. Confirm current amounts with Building Development Services at (956) 794-1625.

Laredo Pool Permit Fee Structure

The pool building permit is a single flat line. A residential plan-check fee may apply but was not captured from the schedule, and pool electrical and the safety barrier are separate. There is no valuation calculation, no percentage surcharge, and no statewide levy, but Ordinance No. 2024-O-247 adds a flat $20.00 technology fee to every residential permit.

Item Fee How It Is Calculated
Swimming pool building permit $64.00 Flat fee from the "Swimming pool" residential line - same at any pool size.
Technology fee (residential) $20.00 Flat fee on every residential permit, added by Ordinance No. 2024-O-247 (applied once here).
Pool permit with technology fee $84.00 $64 building permit + $20 technology fee (exact, before any plan check).
Residential plan-checking fee Not printed A pool plan-check row was not captured - if one applies it is on top of the $84.
Pool electrical (pump, equipment) Separate May draw its own electrical permit - not part of the $84.
Safety barrier (if a block fence) $96.00 all-in Block fence $46 + $30 plan check + $20 technology fee, only if pulled as a separate fence permit.
State / city percentage levy None Texas has no statewide permit levy; Laredo adds no percentage surcharge (the $20 technology fee is a flat amount).

Source: City of Laredo Code of Ordinances, Chapter 7, Section 109.2 Schedule of Permit Fees; technology fee from Ordinance No. 2024-O-247 (amends Sec. 7-2). The fee table carries no single printed effective date; it is the current codified version (Chapter 7 last amended in 2024). The residential plan-checking table was only partly captured (block fence and re-roof rows), so a pool plan-check fee is not shown and not estimated. Confirm the full pool-permit package with Building Development Services at (956) 794-1625.

Worked Examples - Real Pool Projects in Laredo

Because the pool building permit is a flat $64 plus a flat $20 technology fee, the permit cost does not change with pool size or value. What can add to the total is a separate electrical permit, a plan-check fee if one applies, and a separate barrier permit (each separate permit may carry its own $20 technology fee). Figures are from the codified Section 109.2 schedule and Ordinance No. 2024-O-247.

Example 1: In-ground pool, existing compliant barrier

A homeowner installs an in-ground pool on a lot that already has a compliant safety barrier, so no new fence permit is needed.

  • Swimming pool building permit: $64.00
  • Technology fee: $20.00
  • Residential plan-check fee: not shown - confirm
  • Texas state levy: $0.00 (none)
  • Pool permit total: $84.00 (before any plan check / electrical)

The same $84 applies whether the pool is a small plunge pool or a large in-ground pool - it is a flat line, not valuation-based. A pool plan-check fee, if one applies, is added on top; confirm with the department.

Example 2: In-ground pool with a new block-fence barrier

A new pool that also needs a new code-compliant block-fence barrier, pulled as a separate fence permit.

  • Swimming pool building permit: $64.00
  • Technology fee (pool permit): $20.00
  • Block-fence barrier permit ($46 + $30 plan check + $20 technology fee): $96.00
  • Pool + barrier permits: $180.00 (before any pool plan check / electrical)

Whether the barrier must be pulled as a separate block-fence permit is the department's call - some jurisdictions fold it into the pool permit. Because the technology fee applies to every residential permit, a separate barrier permit carries its own $20. Confirm before assuming the $96 applies.

Example 3: Pool with separate electrical permit

A pool whose pump and equipment wiring is pulled as a separate electrical permit.

  • Swimming pool building permit: $64.00
  • Technology fee (pool permit): $20.00
  • Pool electrical permit: separate - confirm rate
  • Total: $84 + electrical (verify)

Section 109.2 does not confirm the residential electrical-permit rate for a pool in the captured text, so this guide does not print an electrical figure. A separate electrical permit may also carry its own $20 technology fee - call (956) 794-1625 to confirm the electrical and any plan-check fees before budgeting.

When This Estimate May Not Apply

The $84 covers the flat $64 pool building permit on the codified Section 109.2 schedule plus the $20 technology fee from Ordinance No. 2024-O-247. Route your project to Building Development Services at (956) 794-1625 before relying on these figures if any of the following applies:

  • A pool plan-check fee applies. The residential plan-checking table was only partly captured, so a pool plan-check fee is not shown on this page. If one applies, it is on top of the $84 - confirm with the department.
  • Your pool needs a new safety barrier. A block-fence barrier is $96 all-in as a separate permit, or it may be folded into the pool permit - the department decides. This guide does not assume one way or the other.
  • Pool electrical is permitted separately. Pump and equipment wiring may draw its own electrical permit, which is not included in the $84.
  • Your pool has a gas heater. Gas-line work may be permitted separately - a question for the department.
  • Your project needs more than one permit. Ordinance No. 2024-O-247 assesses the $20.00 technology fee to "every residential permit." If the job also needs a separate electrical or barrier permit, each permit may carry its own $20. PermitPrice adds it once, for the single pool permit shown.
  • Impact or utility fees apply. Water/sewer tap and impact fees are on separate schedules and are not part of the $84 pool permit.
  • The ordinance is amended. The figures come from a codified schedule with no single printed effective date and can change by amendment - confirm before filing.

Pool electrical, plan-check, barrier, and impact fees are excluded from the $84 pool permit figure on this page, and the page-standard disclaimer applies - always verify with Building Development Services before budgeting.

Laredo Pool Permit Cost vs Other Verified Texas Cities

Texas cities price pool permits on different models - flat building permits, valuation-based fees, and flat fees that bundle trades. The table below compares Laredo's flat pool building permit with other verified Texas cities. Scope differs, so each figure notes its basis.

City Pool Fee Basis Pool Permit
Laredo, TX Flat building permit + $20 tech; trades/plan-check separate $84.00
McAllen, TX Flat pool line $55.86
Brownsville, TX Flat pool line; trades separate $200.00
San Marcos, TX Flat pool + $15 tech; trades separate $286.00

Scope note: Laredo's $84 is the $64 pool building permit plus the $20 residential technology fee, with pool electrical, any plan-check fee, and the barrier separate. McAllen's $55.86 and Brownsville's $200 are flat pool lines, and San Marcos's $286 is a $271 flat pool line plus a $15 technology fee - all with pool electrical billed separately. Laredo and McAllen anchor the low end of verified Texas pool permits. Confirm current figures and trade treatment with each department.

Next Step

See Laredo's full residential fee schedule, or price a fence or re-roof.

Frequently Asked Questions

A residential swimming pool building permit is a flat $64.00, and Ordinance No. 2024-O-247 adds a $20.00 technology fee to every residential permit, for $84.00 - the same at any pool size or value. A residential plan-checking fee for a pool is not printed in the captured schedule, so it is not added here; confirm whether one applies. Pool electrical and a safety barrier are separate. Texas adds no state levy and Laredo adds no percentage surcharge. Figures are from the codified Code of Ordinances (Section 109.2) and Ordinance No. 2024-O-247.
No. Laredo's $64 building permit and $20 technology fee are both flat ($84) - the total is the same whether the pool is a small plunge pool or a large in-ground pool, and it is not tied to construction value. That differs from valuation-based cities like College Station, where the building-side pool fee rises with the pool's value.
No. The $84 is the $64 pool building permit plus the $20 technology fee. Pool pump and equipment wiring may draw a separate electrical permit, and a residential plan-checking fee may also apply - that pool plan-check row was not captured from the schedule, so it is not shown or estimated on this page. Both would be on top of the $84, and a separate electrical permit may carry its own $20 technology fee. Confirm the full package with Building Development Services at (956) 794-1625.
Maybe. Texas requires a compliant safety barrier around a residential pool. Whether Laredo wants that barrier pulled as its own permit - a block-fence barrier is $96 all-in - or folded into the pool permit is a determination for Building Development Services. This guide does not assume one way or the other. See the Laredo fence permit guide and confirm at (956) 794-1625.
Laredo's $84 pool permit ($64 flat building permit + $20 technology fee) is still one of the lowest verified in Texas - above McAllen's $55.86, and well below Brownsville's $200 and San Marcos's $286. All of these bill pool electrical separately, so add each city's electrical permit before comparing all-in. Laredo and McAllen anchor the low end of the verified South Texas set.
They are from the current codified Laredo Code of Ordinances (Chapter 7, Section 109.2) on the official Municode library, captured June 13, 2026. The fee table carries no single printed effective date, so treat the amounts as the current codified version and confirm the latest amendment with the department. Chapter 7 was amended in 2024, including Ordinance No. 2024-O-247, which added the $20.00 residential technology fee effective about December 27, 2024 (sixty days after the October 28, 2024 public hearing). See all Laredo permit fees for the full schedule.

Who to Contact

Department City of Laredo - Building Development Services
Phone (956) 794-1625
Online permits Click2Gov portal (lare-egov.aspgov.com)
Fee schedule Code of Ordinances, Chapter 7, Section 109.2

Sources

Official Sources - Recorded June 2026
Always verify current pool permit fees directly with City of Laredo Building Development Services before budgeting or filing. The figures on this page come from the codified Code of Ordinances, Chapter 7, Section 109.2, which carries no single printed effective date. The $64 is the pool building permit, and the $20 technology fee comes from Ordinance No. 2024-O-247, effective about December 27, 2024; it applies to every residential permit, so a project with more than one permit may pay it more than once (PermitPrice adds it once). A residential plan-check fee for a pool was not captured and is not shown, and pool electrical and the safety barrier are separate. Call (956) 794-1625 to confirm your project's full fees before submitting an application.
Disclaimer: All fee information on PermitPrice is for informational purposes only and is not an official permit quotation. Actual permit fees are determined by City of Laredo Building Development Services at the time of application. The $64.00 swimming pool building permit shown is exact from the codified Section 109.2 schedule, which carries no single printed effective date (Chapter 7 last amended in 2024), and the $20.00 technology fee is exact from Ordinance No. 2024-O-247, which applies it to every residential permit; PermitPrice adds it once for the single permit shown, for $84.00. A residential plan-checking fee for a pool was not captured from the schedule and is not estimated here; pool electrical, a safety barrier, gas-heater permitting, impact and utility tap fees, construction costs, zoning setbacks, and HOA approvals are excluded from the pool building-permit figure on this page. Verify all fees directly with the department before filing.

Written by: Munib Ur Rehman

Data verified against official fee schedule documents.